West Coast Turf began installing our new Santa Ana Bermudagrass on #6 yesterday. They will move on from there to #7, saving #8 for last. Right now they are planting about an acre a day, which should see the project complete on Monday (7/18).
With some sunshine, water and fertilizer we hope to open all of the holes by August 1st.
Thursday, July 14, 2016
Tuesday, July 12, 2016
Phase 2 Begins!
Thursday, July 7, 2016
Project Prep
Phase 2 of the Fairway Improvement Plan begins next week. We are just finalizing all of the project details, gathering the necessary equipment, and going through the schedule with a fine tooth comb. The Kikuyu on # 6 has been sprayed with a selective herbicide and we are seeing great results.
We continue to water holes 6-8, as many of the heads that water the fairways also irrigate the rough areas. We also want to avoid creating a surface that is so hard that we will have problems aerifying.
Aerification and stripping will begin on Monday the 11th and sod will begin to be installed on the 13th.
I will keep you updated as the process moves along.......
Kikuyu 1 week post herbicide (Drive XLR8) |
We continue to water holes 6-8, as many of the heads that water the fairways also irrigate the rough areas. We also want to avoid creating a surface that is so hard that we will have problems aerifying.
Aerification and stripping will begin on Monday the 11th and sod will begin to be installed on the 13th.
I will keep you updated as the process moves along.......